Tunisia - Institutions and Participation

Action 1 - Develop a monitoring and evaluation system with gender-specific indicators for water-related policies

IWRM Dimension: Institutions and Participation
SDG 6.5.1 Question: 2.2d. Gender inclusion in laws/plans
Level: National
Status of action: Awaiting funding
Related SDG Goal: 5. Gender equality, - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 1 Mio. DT
Responsible Agency: BPEH
Timeline for implementation: 3 years
Tunisia - Management Instruments

Action 2 - Implement pro-active drought management under various climate scenarios

IWRM Dimension: Management Instruments
SDG 6.5.1 Question: 3.1e. Disaster risk reduction
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation, 13. Climate action
Budget for action:: 10 Mio. DT
Responsible Agency: DGRE, BPEH DGFIOP, DGEDA
Timeline for implementation: 1-3 years
Tunisia - Institutions and Participation

Action 3 - Operationalise the IWRM Technical Committee (CTGIRE)

IWRM Dimension: Institutions and Participation
SDG 6.5.1 Question: 2.1a. National institutions
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 100,000 DT
Responsible Agency: DGRE
Timeline for implementation: 0.5-2 years
Tunisia - Institutions and Participation

Action 4 - Analyse the social dynamics surrounding water

IWRM Dimension: Institutions and Participation
SDG 6.5.1 Question: 2.1a. National institutions
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation, - 6.B WASH local participation
Budget for action:: 1 Mio. DT
Responsible Agency: DGREE
Timeline for implementation: 3 months - 1 year
Tunisia - Institutions and Participation

Action 5 - Regularly conduct a structured dialogue with water users and citizens

IWRM Dimension: Institutions and Participation
SDG 6.5.1 Question: 2.1c. Public participation - national
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation, - 6.B WASH local participation
Budget for action:: 2 Mio. DT
Responsible Agency: BPEH
Timeline for implementation: 2 years
Tunisia - Institutions and Participation

Action 6 - Strengthen the capacities of stakeholders in IWRM

IWRM Dimension: Institutions and Participation
SDG 6.5.1 Question: 2.1e. Developing IWRM capacity
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 1 Mio. DT
Responsible Agency: DGRE
Timeline for implementation: 2 years
Tunisia - Institutions and Participation

Action 7 - Set up a coordination platform with Algeria for shared waters

IWRM Dimension: Institutions and Participation
SDG 6.5.1 Question: 2.2e. Transboundary institutions
Level: Transboundary
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 7.5 Mio. DT
Responsible Agency: DGRE
Timeline for implementation: 4 years
Tunisia - Management Instruments

Action 8 - Select the most heavily used aquifers to strengthen, modernise and rehabilitate the monitoring network for quantity and quality parameters

IWRM Dimension: Management Instruments
SDG 6.5.1 Question: 3.1a. Water availability monitoring
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.4 Water efficiency, - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 3 Mio. DT
Responsible Agency: DGRE
Timeline for implementation: 2 years
Tunisia - Management Instruments

Action 9 - Improve hydrogeological knowledge of groundwater and the methods for monitoring and protecting these resources

IWRM Dimension: Management Instruments
SDG 6.5.1 Question: 3.1a. Water availability monitoring
Level: Sub-national
Status of action: Awaiting funding
Related SDG Goal: - 6.4 Water efficiency, - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 2 Mio. DT
Responsible Agency: CRDA Sousse
Timeline for implementation: 3 years
Tunisia - Management Instruments

Action 10 - Promote the implementation of nature-based solutions for water security

IWRM Dimension: Management Instruments
SDG 6.5.1 Question: 3.1d. Ecosystems management
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation, - 6.6 Water-related ecosystems
Budget for action:: 2.5 Mio. DT
Responsible Agency: DGEQV
Timeline for implementation: 1.5 years
Tunisia - Financing

Action 11 - Create a fund financed by pollution fines to carry out actions to rehabilitate and decontaminate water bodies

IWRM Dimension: Financing
SDG 6.5.1 Question: 4.2b. Revenues raised for IWRM elements
Level: Sub-national
Status of action: Awaiting funding
Related SDG Goal: - 6.3 Water quality, treatment, safe reuse, - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 0.8 Mio. DT
Responsible Agency: ANPE
Timeline for implementation: 2 years
Tunisia - Financing

Action 12 - Develop an Investment Programme for the Water Sector

IWRM Dimension: Financing
SDG 6.5.1 Question: 4.1a. National budget for infrastructure
Level: National
Status of action: Awaiting funding
Related SDG Goal: 6. Clean water and sanitation, - 6.1 Safe drinking water, - 6.2 Sanitation and hygiene, - 6.3 Water quality, treatment, safe reuse, - 6.4 Water efficiency, - 6.5 Integrated water resources management & transboundary cooperation, - 6.6 Water-related ecosystems
Budget for action:: 0.5 Mio. DT
Responsible Agency: BPEH
Timeline for implementation: 1 year
Tunisia - Institutions and Participation

Action 13 - Define the appropriate scale and approach to water management

IWRM Dimension: Institutions and Participation
SDG 6.5.1 Question: 2.1a. National institutions
Level: National
Status of action: Awaiting funding
Related SDG Goal: - 6.5 Integrated water resources management & transboundary cooperation
Budget for action:: 0.4 Mio. DT
Responsible Agency: BPEH
Timeline for implementation: 1.5 years